The following steps are taken for the installation of electric wires and meters. The process involves many departments and outside agencies. For prompt installation, please ensure all steps have been taken.

For Residential requests please allow 10 working days from inspection to meter install.

For Commercial requests please allow 60 days from initial contact to meter install.

Application Steps Residential Requirements Commercial Requirements

Electric Permit - City of Lethbridge Development Services. (403) 320-3920

Required

Required

Electric Utility, Design Group (Initial Contact - Site requirements) City of Lethbridge Electric Utility, Design and Admin. Call 311, or (403) 320-3111 outside of Lethbridge or email electricdesign@lethbridge.ca

 

Required

Electric Utility, Financial Group - (Contracts, Invoicing) City of Lethbridge Electric Utility, Design and Administration. Call 311, or (403) 320-3111 outside of Lethbridge or email electricdesign@lethbridge.ca

 

Required

Site ID request - see Site ID and Service Request Form. Call 311, or (403) 320-3111 outside of Lethbridge

Required

Required

Electric Service Request - see Site ID and Service Request Form. Call 311, or (403) 320-3111 outside of Lethbridge

Required

Required

Natural Gas Installation Request - ATCO Gas, 410-Stafford Drive North. (403) 310-5678

Required

 

Final Electric Inspection - City of Lethbridge Development Services. (403) 320-3920

Required

Required

Final Connection and Meter Installation - City of Lethbridge Electric Utility, Operations. Call 311, or (403) 320-3111 outside of Lethbridge

Required

Required

To increase installation efficiency, the Electric Utility, ATCO Gas, Shaw Cable, and Telus work together to service all new residential lots. On lots where Gas and Electrical distribution lines are on opposite sides of your property, ATCO Gas may be installed separately, and the Electric Utility will install the other three-party utilities when we receive the electric inspection report.